Government of India has approved a scheme of National Projects to be implemented during the XI Plan (2007–2012) with a view to expedite completion of identified National Projects for the benefit of the people. Such projects will be provided financial assistance by the Government of India in the form of a Central grant, which will be 90% of the estimated cost of such projects for their completion in a time-bound manner.[1]
I. Criteria for selection of National Projects
II. Procedure for inclusion as a National project
III. Funding of the National Project
IV. Work plan and time schedule for completion of National Projects
V. Monitoring of National Projects
VI. Review by steering committee
VII. Evaluation and impact assessment
| Sl. No. | Name of the Project | State | Status |
|---|---|---|---|
| 1 | Gosi Khurd Irrigation Project | Maharashtra | Project is under Execution |
| 2 | Shahpurkandi dam project | Punjab | Project is under Execution |
| 3 | Teesta Barrage Project | West Bengal | Project is under Execution |
| 4 | Saryu Nahar Pariyojna | Uttar Pradesh | Project is under Execution |
| 5 | Indira Sagar Polavaram Project | Andhra Pradesh | Project is under Execution |
| 6 | Lakhwar Vyasi Multipurpose Project | Uttrakhand | Lakhwar as a standalone project (300MW) accepted by TAC. The project was considered by the Investment Clearance Committee of MoWR, RD & GR in its meeting held on 24.2.2016. |
| 7 | Renuka Dam Project | HP | Technical clearances from CWC are to be obtained by HPPCL. Environment Clearance granted by MoEF & CC was under challenge in
NGT. NGT has cited discrepancies in the requirement of land figures (forest and non-forest, Government and Non-Government) |
| 8 | Ujh Multipurpose Project | J & K | DPR under appraisal in CWC/CEA |
| 9 | Kishau Multipurpose Project | HP/Uttrakhand | DPR prepared. MOU for Joint Venture between Govt. Of UK and Govt. Of HP signed. JV SPV yet to be formed. |
| 10 | Ken Betwa Link Project | Madhya Pradesh | Updated cost estimate of the project (2015–16 PL) was submitted in CWC by NWDA in February 2016, which is
under examination. DPR of Phase II is yet to be submitted to CWC by NWDA. |
| 11 | Kulsi Dam Project | Assam | Project is under appraisal in CWC/CEA. Compliance to the observations of CWC/CEA on the DPR of the project are pending. |
| 12 | Noa-Dihing Dam Project | Arunachal Pradesh | Project is under appraisal in CWC/CEA. Compliance to the observations of CWC/CEA on the DPR of the project are pending. |
| 13 | Bursar HE Project | J & K | DPR under preparation by NHPC |
| 14 | Gyspa HE Project | HP | DPR under preparation by Govt. Of Himachal Pradesh |
| 15 | 2nd Ravi Vyas Link Project | Punjab | Under PFR stage. |
| 16 | Upper Siang Project | Arunachal Pradesh | Under PFR stage |
References
- ↑ "Guidelines For Implementation of National Projects" (PDF). mowr.gov.in.
- ↑ "National Project Loksabha Question" (PDF). indiaenvironmentportal.org.in.
External Links
Template:Dams and reservoirs in India Template:Waters of India
This article "National Project of India" is from Wikipedia. The list of its authors can be seen in its historical and/or the page Edithistory:National Project of India. Articles copied from Draft Namespace on Wikipedia could be seen on the Draft Namespace of Wikipedia and not main one.
| This page exists already on Wikipedia. |